ADI-HVM Workpackages, Deliverables and Milestones (Draft)


Dear all - this post shares a first draft of the complete workpackages, activities and deliverables. We are in the process of formalizing / agreeing workpackage ownership and those owners will be working on finalizing their activities / deliverables, estimating the time needed, estimating the workdays needed, determining the worst / most likely / best time requirements plus any risks associated with those.
PROGRAMME MANAGEMENT (DURATION: 36 MONTHS / 1000 DAYS)
  • Day-to-day project organization
  • Day-to-day project marketing and communications
  • Day-to-day management of project technology platforms
  • Day-to-day management of project financial activities
  • Day-to-day data management based on project website content management system (incl. Stakeholder communications)
  • Coordination of project meetings (incl. documentation of activities and results)
  • Coordination of regional workshops and events (incl. documentation of activities and results)
  • Change management of project plan, resources etc.
  • Create / coordinate and submit all necessary reports to funding agency
  • Create / implement intellectual capital reporting framework for activitie and deliverables
  • Create / implement a framework for assessing the flow and exchange of knowledge between higher education, industry and policy makers
  • Continuously assess value for money of activities and deliverables based on intellectual capital reporting principles
  • Manage, monitor, track and forecast budget versus actual cost and schedule
  • Create and implement quality assurance plan
  • Monitor project progress again plan and change manage as necessary
  • Evaluate project during planning, delivery and closure
  • Conduct project risk management
  • Coordinate exploitation of results
  • Organize mini-conferences at the end of each project year
WP 0 PREPARE PROJECT (AIM: 1 MONTH)
  • WP 0.1: Activity - Complete project coordination and administrative requirements
    • WP 0.1: Deliverable - Grant and partner / consortium agreements completed. Payment schedules agreed.
  • WP 0.2: Activity - Review and refresh project focus and deliverables as appropriate
    • WP 0.2: Deliverable - Project plan updated and information / briefing pack created.
  • WP 0.3: Activity - Setup and configure project server
    • WP 0.3: Deliverable - Project server setup and configured
  • WP 0.4: Activity - Select initial simulation software for orientation, onboard and train participants (i.e. www.insightmaker.com)
    • WP 0.4: Deliverable - Simulation software selected and initial web based version for development purposes available
  • WP 0.5: Activity - Confirm participant readiness
    • WP 0.5: Deliverable - Resourcing schedules confirmed by participants
  • WP 0.6: Activity - Confirm project member understanding of legal agreements between lead proposer and funding authorities, and legal agreements between project members and lead proposer.
    • WP 0.6: Deliverable - Training event resulting in formal confirmation by project members
  • WP 0.7: Activity - Confirm project member understanding of intellectual property rights handling during project
    • WP 0.7: Deliverable - Training event resulting in intellectual property agreement by project members
  • WP 0.8: Activity - Train project members on required project administration and financial processes (including eligibility of costs for re-imbursement)
    • WP 0.8: Deliverable - Training event resulting in formal confirmation by project members
  • WP 0.9: Activity - Launch project risk register
    • WP 0.9: Deliverable - Project risk register and review process launched
  • WP 0.10: Activity - Launch project communications plan (including website, intranet and social media marketing)
    • WP 0.10: Deliverable - Communications plan launched
  • WP 0.11: Activity - Launch project governance with meeting schedules and ways of work
    • WP 0.11: Deliverable - Project governance launched
  • WP 0.12: Activity - Conduct three day face-to-face kick-off project meeting in Germany.
    • WP 0.12: Deliverable - Three day face-to-face kick-off event completed
  • WP 0.13: Activity - Launch hiring processes as necessary to fill resource gaps
    • WP 0.13: Deliverable - Launch of hiring processes confirmed
  • WP 0.14: Activity - Organize WP1 and WP 3 workshop schedules
    • WP 0.14: Deliverable - Workshop schedules confirmed
  • WP 0.15: Activity - Train all project participants in project methodology
    • WP 0.15: Deliverable - Training and capability of all participants confirmed
  • WP 0.16: Activity - Prepare workpackage completion and project progress report
    • WP 0.16: Milestone & Deliverable - Progress report finalized and reviewed
WP 1 CREATE SIMULATOR (AIM: 9 MONTHS)
  • WP 1.1: Activity - Create initial simulation model and generic input template based on product lif cycle management software from key players such as Siemens and SAP (Note: May be within Vensim.com PLE but populated through import of Excel based template. Includes instances for Development, Test and Production with relevant change management processes - may be managed via Sourceforge)
    • WP 1.1: Deliverable - Initial simulation model and generic input template
  • WP 1.2: Activity - Conduct half-day workshops with participating companies to train them in the workpackage approach and gather needed whole product life cycle information.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 1.2: Deliverable - Participating companies on-boarded and input to simulation from practice gathered.
  • WP 1.3: Activity - Convert whole product life cycles of participating companies into a phased aggregated process model.
    • WP 1.3: Deliverable - Simulation updated with product life cycle information from participating companies.
  • WP 1.4: Activity - Convert the aggregated process model into a phased value network (innovation web).
    • WP 1.4: Deliverable - Phased value network (innovation web) created.
  • WP 1.5: Activity - Convert the value network into a phased process based system dynamics model.
    • WP 1.5: Deliverable - Phased process created and translated into system dynamics model structure.
  • WP 1.6: Activity - Create a phased systemic performance indicator based system dynamics model.
    • WP 1.6: Deliverable - System dynamics model base don performance indicators (including innovation web measures and default threshold structures).
  • WP 1.7: Activity - Create an aggregated systemic performance indicator based system dynamics model.
    • WP 1.7: Deliverable - Aggregated (simplified / nested) system dynamics model of performance indicators created.
  • WP 1.8: Activity - Create a pilot simulator at the middle of the workpackage (including detailed handbook, application training materials and a handbook of most relevant scenario and gaming exercises).
    • WP 1.8: Deliverable - Pilot simulator and supporting materials created).
  • WP 1.9: Activity - Train project participants in the pilot simulator.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 1.9: Deliverable - Project participants trained in pilot simulator.
  • WP 1.10: Activity - Transfer pilot simulator to the workpackage “Refresh Needs Analysis and Prepare Case Studies.” at the middle of the workpackage.
    • WP 1.10: Deliverable - Pilot simulator transferred to workpackage 6.
  • WP 1.11: Activity - Conduct half-day workshops with participating companies to validate results and train them in the pilot simulator.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 1.11: Deliverable - Pilot simulator validated and feedback from participating companies integrated. Participating companies trained.
  • WP 1.12: Activity - Create initial full version of simulator at the end of the workpackage (including detailed handbook, application training materials and a handbook of most relevant scenario and gaming exercises).
    • WP 1.12: Deliverable - Full version of Simulator (including all documentation and training materials created)
  • WP 1.13: Activity - Train project participants in the initial full version of the simulator.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 1.13: Deliverable - All project participant trained in full version of simulator.
  • WP 1.14: Activity - Conduct final validation workshops with participating companies.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 1.14: Deliverable - Final validation workshops with participating companies completed.
  • WP 1.15: Activity - Train participating manufacturing companies in the initial full version of the simulator.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 1.15: Deliverable - Participating companies trained in full simulator.
  • WP 1.16: Activity - Create an online version of the simulation which is free for non-commercial use at the end of year 2 of the project.
    • WP 1.16: Deliverable - Online version of simulator launched.
  • WP 1.17: Activity - Prepare workpackage completion and project progress report
    • WP 1.17: Milestone & Deliverable - Progress report finalized and reviewed
WP 2 NEEDS ANALYSIS (AIM: 6 MONTHS)
  • WP 2.1 Activity - Conduct scenario analysis (incl. needs and expectations of SMEs, needs and expectations of direct target groups, available training courses)
    • WP 2.1 Deliverable - Documented scenario analysis
  • WP 2.2 Activity - Conduct statistical analysis (incl. sector’s occupancy rate, number of people who attend relevant courses, number of attendants employed after obtaining the course certificate, number of SMEs in partners countries)
    • WP 2.2 Deliverable - Documented statistical analysis
  • WP 2.3 Activity - Share interim outcomes
    • WP 2.3 Deliverable - Scenario and statistical analysis consolidated and shared
  • WP 2.4: Activity - Conduct a literature review related to the speed of innovation diffusion in manufacturing (including relevant policy perspectives) and prepare journal article submission of results.
    • WP 2.4: Deliverable - Literature review and journal submission completed.
  • WP 2.5: Activity - Solicit input from all project participants for improving the needs analysis with an enhanced focus on higher education and the call requirements.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 2.5: Deliverable - Input from all project participants for improving the needs analysis with an enhanced focus on higher education and the call requirements received.
  • WP 2.6: Activity - Revise the needs analysis completed as part of proposal preparation based upon workpackage 1 results (semi-structured interviews and online survey tool).
    • WP 2.6: Deliverable - Input for needs analysis gathered and needs analysis revised.
  • WP 2.7: Activity - Reconduct the needs analysis with participating manufacturing companies and higher education institutions.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 2.7: Deliverable - Needs analysis refreshed and project structure adapted as necessary.
  • WP 2.8: Activity - Extend the needs analysis through coordination with project participants and their networks.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 2.8: Deliverable - Needs analysis extended through coordination with project participants and their networks.
  • WP 2.9: Activity - Create high level manufacturing case studies from participating manufacturing companies demonstrating how the results of the needs analysis support the value proposition of the project to industry, higher education and (regions of) the EU as a whole. Prepare a conference article to disseminate the results to a wider audience.
    • WP 2.9: Deliverable - High level manufacturing case studies completed and conference contribution submitted.
  • WP 2.10: Activity - Feedback improvement suggestions to workpackage 1 for the simulation tool.
    • WP 2.10: Deliverable - Improvement suggestions provided to workpackage 1 for the simulation tool.
  • WP 2.11: Activity - Prepare and hand-over design guidelines for the living labs to be conducted in workpackage 3 “Conduct Case Studies (as Living Labs)”
    • WP 2.11: Deliverable - Design guidelines handed over for the living labs to be conducted in workpackage 3 “Conduct Case Studies (as Living Labs)”
  • WP 2.12: Activity - Prepare workpackage completion and project progress report
    • WP 2.12: Milestone & Deliverable - Progress report finalized and reviewed
WP 3 CONDUCT CASE STUDIES (AS LIVING LABS) (AIM: 6 MONTHS)
  • WP 3.1: Activity - Finalize design guidelines for living labs provided by workpackage 2.
    • WP 3.1: Deliverable - Design guidelines for living labs provided by workpackage 2 finalized.
  • WP 3.2: Activity - Prepare (regional) three day living labs at participating manufacturing organizations and participating higher education institutions considering the (ongoing) work of workpackages 1 and 2.
    • WP 3.2: Deliverable - (Regional) three day living labs prepared.
  • WP 3.3: Activity - Conduct three day living labs at participating manufacturing organizations and participating higher education institutions.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 3.3: Deliverable - Three day living labs conducted.
  • WP 3.4: Activity - Create case studies for each of the living labs and combine these in a conference contribution.
    • WP 3.4: Deliverable - Case studies created and conference contribution prepared.
  • WP 3.5: Activity - Provide input for finalizing workpackages 1 and 2.
    • WP 3.5: Deliverable - Input for workpackages 1 and 2 finalized.
  • WP 3.6: Activity - Provide input to workpackages 6, 7 and 8.
    • WP 3.6: Deliverable - Input provided to workpackages 6, 7 and 8.
  • WP 3.7: Activity - Prepare and hand-over design guidelines for the living labs to be conducted in workpackage 3 “Conduct Case Studies (as Living Labs)”
    • WP 3.7: Deliverable - Design guidelines for the living labs to be conducted in workpackage 3 “Conduct Case Studies (as Living Labs)” handed over
    • WP 3.7: Milestone & Deliverable - Progress report finalized and reviewed
WP 4 IDENTIFY VARIABLES AND GAME CHANGERS (AIM: 9 MONTHS)
  • WP 4.1: Activity - Validate the system dynamics model based on standard procedures.
    • WP 4.1: Deliverable - System dynamics model validated.
  • WP 4.2: Activity - Define model objectives.
    • WP 4.2: Deliverable - Model objectives defined.
  • WP 4.3: Activity - Define input parameters.
    • WP 4.3: Deliverable - Input parameters defined
  • WP 4.4: Activity - Define key analysis scenarios
    • WP 4.4: Deliverable - Key analysis scenarios defined
  • WP 4.5: Activity - Conduct case study based analyses to validate model performance.
    • WP 4.5: Deliverable - Case study based analyses to validate model performance completed.
  • WP 4.6: Activity - Identify co-variances of model variables.
    • WP 4.6: Deliverable - Co-variances of model variables defined.
  • WP 4.7: Activity - Design and conduct experiments to determine current tipping points.
    • WP 4.7: Deliverable - Experiments to determine current tipping points conducted.
  • WP 4.8: Activity - Implement key analysis scenarios in order to correlate whole product life cycle changes with changes of simulation results.
    • WP 4.8: Deliverable - Key analysis scenarios implemented.
  • WP 4.9: Activity - Based upon the results of the scenario analysis determine actionable whole product life cycle changes to accelerate innovation diffusion.
    • WP 4.9: Deliverable - Actionable whole product life cycle changes to accelerate innovation diffusion identified.
  • WP 4.10: Activity - Develop guidelines on simulation usage for workpackage 5 “Create Risk and Uncertainty Reduction Framework”
    • WP 4.10: Deliverable - Guidelines on simulation usage for workpackage 5 “Create Risk and Uncertainty Reduction Framework” created.
  • WP 4.11: Activity - Develop guidelines on simulation usage for workpackage 6 “Create Design Principles for Rapid Diffusion of Innovative Ideas.”
    • WP 4.11: Deliverable - Guidelines on simulation usage for workpackage 6 “Create Design Principles for Rapid Diffusion of Innovative Ideas.” created.
    • WP 4.11: Milestone & Deliverable - Progress report finalized and reviewed
WP 5 CREATE RISK AND UNCERTAINTY REDUCTION FRAMEWORK (AIM: 9 MONTHS)
  • WP 5.1: Activity - Conduct a literature research on inverse uncertainty quantification approaches applicable to the diffusion of innovations from ideation through market saturation. Submit the results as a journal publication.
    • WP 5.1: Deliverable - Literature review and journal submission.
  • WP 5.2: Activity - Conduct PESTLE analysis regarding influencers of innovation system simulation and embed in simulation.
    • WP 5.2: Deliverable - PESTLE analysis and updated simulation.
  • WP 5.3: Activity - Create a method for estimating the uncertainties of simulation results.
    • WP 5.3: Deliverable - Uncertainty estimation method (embedded in simulation)
  • WP 5.4: Activity - Develop a structured series of interventions for accelerating the innovation system performance (based on the principles of the tool "KMAP" by Karl-Erik Sveiby)
    • WP 5.4: Deliverable - Intervention tool.
  • WP 5.5: Activity - Create a generic scoring scheme for assessing the risk threat and opportunity probabilities and impacts (includes definition of relevant assessment variables and ranges).
    • WP 5.5: Deliverable - Generic scoring scheme embedded in intervention tool.
  • WP 5.6: Activity - Create an approach for visualizing risk and uncertainty progression (including impact of treatment).
    • WP 5.6: Deliverable - Visualization approach created and embedded in intervention and simulation tool.
  • WP 5.7: Activity - Summarize and publish framework as a conference contribution.
    • WP 5.7: Deliverable - Workpackage results published as conference contribution.
  • WP 5.8: Activity - Develop guidance for workpackage 6 “Create Design Principles for Rapid Diffusion of Innovative Ideas.”
    • WP 5.8: Milestone & Deliverable - Progress report finalized and reviewed
WP 6 CREATE DESIGN PRINCIPLES FOR RAPID DIFFUSION OF INNOVATIVE IDEAS (AIM: 9 MONTHS)
  • WP 6.1: Activity - Gather previous insights gained on key attributes of (clusters of) ideas for diffusing rapidly from ideation through market saturation (incl. simulation learning).
    • WP 6.1: Deliverable - Previous insights gathered on key attributes of (clusters of) ideas for diffusing rapidly from ideation through market saturation (incl. simulation learning).
  • WP 6.2: Activity - Conduct a literature research on key attributes of (clusters of) ideas for diffusing rapidly from ideation through market saturation, including insights gained from previous workpackages. Submit the results as a journal publication.
    • WP 6.2: Deliverable - Literature research on key attributes of (clusters of) ideas for diffusing rapidly from ideation through market saturation, including insights gained from previous workpackages. Results submitted as a journal publication.
  • WP 6.3: Activity - Identify a range of actionable principles for designing (clusters of) ideas that are suited for rapid diffusion through the whole product life cycle.
    • WP 6.3: Deliverable - Range of actionable principles identified for designing (clusters of) ideas that are suited for rapid diffusion through the whole product life cycle.
  • WP 6.4: Activity - Develop and validate a technique for testing the diffusion of innovation speed within the simulator. Submit the results as a journal publication.
    • WP 6.4: Deliverable - A technique for testing the diffusion of innovation speed within the simulator. Results submitted as a journal publication.
  • WP 6.5: Activity - Validate design principles based upon previously generated case studies in one day workshops with six industrial companies and six institutes of higher education.
    • WP 6.5: Deliverable - Design principles validated based upon previously generated case studies.
  • WP 6.6: Activity - Develop guidance for workpackage 7 (“Validate Research Findings (as Experimental Innovation in Living Labs”) and workpackage 8 (“Discover and Launch Ideas in a Structured Manner (incl. Innovation Diffusion Monitoring Radar)”. Prepare as conference contribution.
    • WP 6.6: Deliverable - Guidance for workpackage 7 (“Validate Research Findings (as Experimental Innovation in Living Labs”) and workpackage 8 (“Discover and Launch Ideas in a Structured Manner (incl. Innovation Diffusion Monitoring Radar)”. Conference contribution prepared.
    • WP 6.6: Milestone & Deliverable - Progress report finalized and reviewed
WP 7 VALIDATE RESEARCH FINDING (AS EXPERIMENTAL INNOVATION IN LIVING LABS) (AIM: 9 MONTHS)
  • WP 7.1: Activity - Review and adapt design guidelines for ideas provided by workpackage 6.
    • WP 7.1: Deliverable - Design guidelines for ideas provided by workpackage 6 reviewed and adapted
  • WP 7.2: Activity - Prepare three day living labs with a focus on experimental innovation at six participating manufacturing organizations and six participating higher education institutions considering the results of all previous workpackages.
    • WP 7.2: Deliverable - Three day living labs with a focus on experimental innovation at participating manufacturing organizations and participating higher education institutions considering the results of all previous workpackages prepared
  • WP 7.3: Activity - Conduct three day living labs at six participating manufacturing organizations and six participating higher education institutions.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 7.3: Deliverable - Three day living labs at participating manufacturing organizations and participating higher education institutions conducted.
  • WP 7.4: Activity - Finalize design guidelines and simulator.
    • WP 7.4: Deliverable - Design guidelines and simulator finalized.
  • WP 7.5: Activity - Prepare and hand-over design guidelines for the structured ideation approach in workpackage 8 “Discover and Launch Ideas in a Structured Manner (incl. Innovation Diffusion Monitoring Radar).”
    • WP 7.5: Deliverable - Design guidelines for the structured ideation approach in workpackage 8 “Discover and Launch Ideas in a Structured Manner (incl. Innovation Diffusion Monitoring Radar).” finalized and handed over.
    • WP 7.5: Milestone & Deliverable - Progress report finalized and reviewed
WP 8 DISCOVER AND LAUNCH IDEAS IN A STRUCTURED MANNER (INCLUDING INNOVATION DIFFUSION RADAR) (AIM: 9 MONTHS)
  • WP 8.1: Activity - Review and adapt design guidelines for ideas provided by workpackage 6 based on experiences in workpackage 7.
    • WP 8.1: Deliverable - Design guidelines for ideas provided by workpackage 6 based on experiences in workpackage 7 revised and adapted
  • WP 8.2: Activity - Prepare one day events with a focus on structured ideation and diffusion monitoring at six participating manufacturing organizations and six participating higher education institutions considering the results of all previous workpackages.
    • WP 8.2: Deliverable - One day events prepared
  • WP 8.3: Activity - Conduct one day events at six participating manufacturing organizations and six participating higher education institutions.
      • ** Host: Baltics (Latvia) - Riga
      • ** Host: Germany - Zweibrücken
      • ** Host: Ireland - Dublin
      • ** Host: Israel - Tel Aviv
      • ** Host: Italy - Padova
      • ** Host: Luxembourg - Luxembourg
      • ** Host: Poland - Rzeszowska
      • ** Host: Portugal - Lisbon
      • ** Host: Slovakia - Kosice
    • WP 8.3: Deliverable - One day events conducted
  • WP 8.4: Activity - Finalize design guidelines and simulator.
    • WP 8.5: Deliverable - Design guidelines and simulator finalized.
  • WP 8.5: Activity - Develop and implement innovation monitoring diffusion radar for ideas.
    • WP 8.5: Deliverable - Innovation monitoring diffusion radar for ideas developed and implemented
    • WP 8.5: Milestone & Deliverable - Progress report finalized and reviewed
WP 9 CREATE AND PILOT VOCATIONAL AND HIGHER EDUCATION CAREER FRAMEWORK (AIM: 9 MONTHS)
  • WP 9.1: Activity - Create / Deploy Accredited Educational Offerings (incl. Policy Guidance):
    • WP 9.1: Deliverable - Accredited Educational Offerings (incl. Policy Guidance) created and deployed
  • WP 9.2: Activity - Select (online) training and content management platform (i.e. Moodle)
    • WP 9.2: Deliverable - (Online) training and content management platform (i.e. Moodle) selected
  • WP 9.3: Activity - Convert workpackage deliverables into (online) training offerings for higher education (innovation and entrepreneurship focus)
    • WP 9.3: Deliverable - Workpackage deliverables into (online) training offerings for higher education (innovation and entrepreneurship focus) converted
  • WP 9.4: Activity - Convert workpackage deliverables into (online) training offerings for industry (innovation and entrepreneurship focus)
    • WP 9.4: Deliverable - Workpackage deliverables into (online) training offerings for industry (innovation and entrepreneurship focus) converted
  • WP 9.5: Activity - Convert workpackage deliverables into (online) training offerings for policy makers  (innovation and entrepreneurship focus)
    • WP 9.5: Deliverable - Workpackage deliverables into (online) training offerings for policy makers  (innovation and entrepreneurship focus) converted
    • WP 9.5: Milestone & Deliverable - Progress report finalized and reviewed
If you are interested in learning more please visit us at www.innovation-web.eu, our LinkedIn Group at https://www.linkedin.com/groups/8779542/, our blog at https://www.innovation-web.eu/entov-hvm-blog, our Researchgate project page at https://www.researchgate.net/project/Open-European-Network-for-Enterprise-Innovation-in-High-Value-Manufacturing-ENTOV-HVM and our Facebook page at: https://www.facebook.com/groups/2014779865300180/. You can also follow us via Twitter: @owschwabe (#innovationweb) and the LinkedIn Group page https://www.linkedin.com/company/entov.
 

Kommentare

Beliebte Posts aus diesem Blog

Roundtable “Improving City Cybersecurity – Accelerating the Sharing of Sensitive Personal Knowledge “- April 21 at 4PM CET

Business Invitation to Join Us in Our eGoose Proposal - Aspiring to "Instant" CyberSafety in EU Manufacturing SME Ecosystems

Exploring the Second Innovation Web: The Socialization (Community Building) Archetype