ENTOV-HVM: Key Risks and Possible Treatments
This blog post is a draft response to “Section 4 Implementation
/ 4.1 Coherence and Effectiveness of the Work Plans / Section 4.1.3 Risk Analysis and Contingency Plans” in the
technical annex of the planned COST 2019 Open Call Proposal Reference:
OC-2019-1-23678 "Open European Network for Enterprise Innovation in High
Value Manufacturing (ENTOV-HVM)".
The image shows a life guard tower in Venice, California to
exemplify the perspective that effective risk and uncertainty management are
core to successful project execution (retrieved from http://www.towleroad.com/2017/10/rainbow-lifeguard-tower-2/).
The following table is an excerpt from the ENTOV-HVM risk
register which highlights the key (high) risks and / or possible issues to the
proposed ENTOV-HVM actions and point to relevant probabilities, impact,
including potential treatments.
Risk and / or possible issues
|
Probability
|
Impact
|
Treatment
|
The minimum viable pairs of participant (senior
and early career) in the innovation web commercialization archetype roles
(including needed web weavers) is not achieved.
|
High
|
High
|
Intensify
requests for existing viable participants to recommend individuals in their
trusted network. Ensure that participants only apply for a role in relevant
pairs.
|
The participants in the innovation web
roles (including web weavers) do not meet the behavioural requirements for
healthy exchange of tangible and deliverable exchanges.
|
High
|
High
|
Increase rigor of approving
participant (pair) participation in formal project roles since this behaviour
cannot be trained as part of the ENTOV-HVM effort. The use of living system
principles to self-selection is promising yet creates tensions with formal
schedule planning.
|
Minimum required work effort to meet the
number of intended deliverables is not provided due to lack of sufficient resources
(i.e. funding of staff position at proposer institutions)
|
High
|
High
|
Ensure
sufficient momentum in soliciting further grants and / or industry project
funding in order to fund required work effort. Do not launch work efforts at
risk.
|
Proposer institutions in COST Target Inclusiveness
Countries are unable to solicit participation in training schools, joint
research-industry workshops and innovation cohorts.
|
High
|
High
|
Apply short-interval
monitoring and ensure the complete network pro-actively supports relevant
marketing and recruitment measures. Each event should be driven forward by
all network members and crystalize at the relevant proposer institution in
the COST Target Inclusiveness Country.
|
Workgroup efforts and project deliverables do
not meet the needs of the role participants
|
High
|
High
|
Web
weavers need to ensure that pair-therapy approaches are taken to improving
the relationships between relevant participants, including discovery of “true”
needs.
|
ENTOV-HVM does not have sufficient
resources to manage the very high collaboration / coordination facilitation
which is required due to the complex nature of the challenge being addressed.
|
High
|
High
|
ENTOV-HVM is a complex
effort and the collaboration / coordination overhead is expected to exceed
25% of direct deliverable related effort. This needs to be factored into
project planning from the outset.
|
ENTOV-HVM does not have sufficient
resources to manage the churn of participants due to the “open” nature of the
effort.
|
High
|
High
|
By
design ENTOV-HVM is “open” and a significant churn of participants is
expected. This must be addressed by maintaining budgeted collaboration /
coordination efforts during the whole project life cycle.
|
To join the network please visit our LinkedIn Group at
https://www.linkedin.com/groups/8779542/
Kommentare
Kommentar veröffentlichen